Central Information Commission
Parsa vs Gail Gas Limited on 19 June, 2019Author: Bimal Julka के ीय सूचना आयोग Central Information Commission बाबा गंगनाथ माग, मुिनरका Baba Gangnath Marg, Munirka नई द ली, New Delhi – 110067
ि तीय अपील सं या / Second Appeal No.:- CIC/GAILG/A/2018/124902-BJ
Mr. Parsa ….अपीलकता /Appellant VERSUS बनाम
1. CPIO
Gail Gas Ltd.
Corporate Office: 13th & 14th Floor
Gail Jubilee Tower, B 35 & 36
Sector – 1, Noida – 201301, Uttar Pradesh 2. CPIO
Ministry of Petroleum and Natural Gas
Shastri Bhawan, New Delhi – 110001 … ितवादीगण /Respondent Date of Hearing : 18.06.2019
Date of Decision : 19.06.2019 Date of RTI application 01.02.2018
CPIO’s response 09.03.2018
Date of the First Appeal 12.03.2018
First Appellate Authority’s response 06.04.2018
Date of diarised receipt of Appeal by the Commission 19.04.2018 ORDER
FACTS:
The Appellant vide his RTI application sought information on 05 points regarding the allocation of
1.1 MMSCMD domestic gas by MoPNG, name of the beneficiary to whom the aforementioned
Domestic Gas, category under which it was allocated, etc. The CPIO, GAIL, vide its letter dated 09.03.2018 provided a point wise response to the Appellant.
Dissatisfied by the response, the Appellant approached the FAA. The FAA, M/o Petroleum and
Natural Gas vide its order dated 06.04.2018 transferred the First Appeal to the FAA, GAIL.
HEARING:
Facts emerging during the hearing:
The following were present:
Page 1 of 5
Appellant: Mr. Parsa through VC;
Respondent: Mr. Ranveer Singh, GM (Mktg.), GAIL, Mr. S. S. Pangti, CPIO, GAIL and
Mr. Sanjay Dixit, DGM, GAIL and Mr. Raj Kishore, US (GP), MoPNG;
The Appellant reiterated the contents of the RTI application and stated that the information sought
was intentionally and arbitrarily denied to him and that pointed queries raised by him were replied in
a vague and misleading manner and that details regarding the name of the beneficiary to whom 1.1
MMSCMD domestic gas had been allocated by MoP&NG, category under which it was allocated
etc. was not disclosed to him. He also referred to the reply provided by the GAIL officials wherein
for points 02 to 05 it was conveyed that the information was not available at site office (Agra)
without making any effort to retrieve the information from the Head Office where it was available by
seeking assistance under Section 5 (4) / 6(3) of the RTI Act, 2005. In its reply, the Respondent
(GAIL) reiterated the reply of the CPIO and stated that a copy of letter dated 29.09.2011 regarding
transfer of APM location made to GAIL for Agra, Firozabad to GAIL Gas Ltd. was already disclosed
to the Appellant which answered point No. 01 of his RTI application. In addition a reference was
also drawn to the text of the correspondence held between MoP&NG and GAIL Gas Ltd. wherein on
05.03.2014, it was informed that there was no allocation of domestic gas to individual industries in
TTZ unlike rest of the Country, prorata cut, envisaged in its guidelines dated 03.02.2014 would not
apply to individual customers of TTZ in the same fashion as it would apply to other direct individual
industrial customers. It was clarified that uniform price mechanism (UPM Policy) would continue to
remain applicable for industrial customers in TTZ. Besides this several other correspondences
between the year 1995 to 2000 were also referred to. As regards the remaining points, it was
conveyed that the information sought was not available in the Agra Office hence could not be
provided. On being queried by the Commission regarding the reason for not transferring the RTI
application under Section 6 (3) of the RTI Act, 2005 to the appropriate Public Authority or for not
taking assistance of the concerned officials within the public authority under Section 5 (4) of the RTI
Act, 2005, no satisfactory response was provided by the Respondent (GAIL). In its reply, the
Respondent, MoPNG stated that no such category as desired by the Appellant in point no. 02 of the
RTI application existed and that allocation was made based on Sectoral classification which was a
dynamic process considering the changing priorities of various sectors. On being queried by the
Commission regarding the response to the other remaining points of the RTI application, no
satisfactory reply was offered by the Ministry official. The Commission was in receipt of a written
submission from the Respondent (M/o Petroleum and Natural Gas, New Delhi) dated 13.06.2019
wherein the reply of the CPIO/ FAA against the RTI Application/ First Appeal was re-iterated.
Having heard both the parties and on perusal of the available records, the Commission observed that
the Appellant had raised specific and pointed queries in his RTI application which were not answered
clearly and cogently by the officials of both the Public Authorities i.e. MoP&NG and GAIL Gas Ltd.
which was in contravention to the provisions of the RTI Act, 2005. In this context, the Commission
observed that as per the provisions of Section 19 (5) of the RTI Act, 2005, in an Appeal proceeding,
the onus to prove that a denial of a request was justified shall be on the CPIO who could not justify
his position in the matter.
Moreover, as per the provisions of Section 7 (8) (i) of the RTI Act, 2005, where a request for
disclosure of information is rejected, the CPIO shall communicate the reasons for such rejection.
In the present instance the transfer of RTI application u/s 6 (3) of the Act had not been made by the
GAIL Gas Ltd. to the appropriate Public Authority for point Nos. 02 to 05 of the RTI application.
Even assuming that the application was transferred, it cannot be said that the transferring authority
can be completely absolved of his duties and responsibilities as CPIO thereafter. In this context, a Page 2 of 5 reference can be made to the decision of the Hon’ble Delhi High Court in J P Aggarwal v. Union of
India (WP (C) no. 7232/2009 wherein it was held that:
” 7″it is the PIO to whom the application is submitted and it is who is responsible for ensuring that the information as sought is provided to the applicant within the statutory requirements of the Act. Section 5(4) is simply to strengthen the authority of the PIO within the department; if the PIO finds a default by those from whom he has sought information. The PIO is expected to recommend a remedial action to be taken”. The RTI Act makes the PIO the pivot for enforcing the implementation of the Act.”
8………….The PIO is expected to apply his / her mind, duly analyse the material before him / her and then either disclose the information sought or give grounds for non-disclosure.”
Furthermore, in Ministry Of Railways Through … vs Girish Mittal on 12 September, 2014 W.P.(C)
6088/2014 & CM Nos.14799/2014, 14800/2014 & 14801/2014, the Hon’ble High Court of Delhi
held as under:
“15. The plain language of Section 6(3) of the Act indicates that the public authority would transfer the application or such part of it to another public authority where the information sought is more closely connected with the functions of the other authority. The reliance placed by the learned counsel for the petitioner on the provisions of Section 6(3) of the Act is clearly misplaced in the facts and circumstances of the case. This is not a case where penalty has been imposed with respect to queries which have been referred to another public authority, but with respect to queries that were to be addressed by the public authority of which petitioner no. 2 is a Public Information Officer. Section 6(3) of the Act cannot be read to mean that the responsibility of a CPIO is only limited to forwarding the applications to different departments/offices. Forwarding an application by a public authority to another public authority is not the same as a Public Information Officer of a public authority arranging or sourcing information from within its own organisation. In the present case, undisputedly, certain information which was not provided to respondent would be available with the Railway Board and the CPIO was required to furnish the same. He cannot escape his responsibility to provide the information by simply stating that the queries were forwarded to other officials.”
A reference can also be made to a recent decision of the High Court of Delhi in the matter of Shikha
Bagga Vs. Public Information Officer, Directorate of Education and Another’s, in W. P. (C)
4172/2017 dated 13.07.2017 wherein it was held as under:
“4. Clearly, transferring the petitioner’s application to various schools is unsustainable. The PIO is required to provide all such information as sought for, subject to the exceptions as provided under the Act 5. In the circumstances, the writ petition is allowed and the impugned letters/orders dated 18.04.2017 and 22.04.2017 transferring the petitioner’s application to various officers and various schools are set aside. It is directed that the petitioner’s application be considered by respondent no.1 in accordance with law”
The Commission also observed that the RTI Act, 2005 stipulates time limits in its various provisions
relating to responding to RTI Applications, transfer of applications, filing and disposing of first
appeal to ensure that a culture of information dissemination is strengthened so that a robust
functioning of the democracy gets established. This was recognised by the Hon’ble High Court of Page 3 of 5 Delhi in Mujibur Rehman vs Central Information Commission (W.P. (C) 3845/2007)(Dated 28 April,
2009) wherein it was held as under:
“14…….The court cannot be unmindful of the circumstances under which the Act was framed, and brought into force. It seeks to foster an “openness culture” among state agencies, and a wider section of “public authorities” whose actions have a significant or lasting impact on the people and their lives. Information seekers are to be furnished what they ask for, unless the Act prohibits disclosure; they are not to be driven away through sheer inaction or filibustering tactics of the public authorities or their officers. It is to ensure these ends that time limits have been prescribed, in absolute terms, as well as penalty provisions. These are meant to ensure a culture of information disclosure so necessary for a robust and functioning democracy.”
Furthermore, the Hon’ble High Court of Delhi in the matter of R.K. Jain vs Union of India, LPA No.
369/2018, dated 29.08.2018, held as under:
“9………………………….. That apart, the CPIO being custodian of the information or the documents
sought for, is primarily responsible under the scheme of the RTI Act to supply the information and in
case of default or dereliction on his part, the penal action is to be invoked against him only.”
With regard to the imposition of penalty on the CPIO/PIO under Section 20 of the RTI Act, 2005, the
Commission took note of the ruling of Hon’ble Delhi High Court in W.P.(C) 11271/2009 Registrar
of Companies & Ors v. Dharmendra Kumar Garg & Anr. (delivered on: 01.06.2012) wherein it was
held:
” 61. Even if it were to be assumed for the sake of argument, that the view taken by the learned Central Information Commissioner in the impugned order was correct, and that the PIOs were obliged to provide the information, which was otherwise retrievable by the querist by resort to Section 610 of the Companies Act, it could not be said that the information had been withheld malafide or deliberately without any reasonable cause. It can happen that the PIO may genuinely and bonafidely entertain the belief and hold the view that the information sought by the querist cannot be provided for one or the other reasons. Merely because the CIC eventually finds that the view taken by the PIO was not correct, it cannot automatically lead to issuance of a showcause notice under Section 20 of the RTI Act and the imposition of penalty. The legislature has cautiously provided that only in cases of malafides or unreasonable conduct, i.e., where the PIO, without reasonable cause refuses to receive the application, or provide the information, or knowingly gives incorrect, incomplete or misleading information or destroys the information, that the personal penalty on the PIO can be imposed. This was certainly not one such case. If the CIC starts imposing penalty on the PIOs in every other case, without any justification, it would instill a sense of constant apprehension in those functioning as PIOs in the public authorities, and would put undue pressure on them. They would not be able to ful fill their statutory duties under the RTI Act with an independent mind and with objectivity. Such consequences would not auger well for the future development and growth of the regime that the RTI Act seeks to bring in, and may lead to skewed and imbalanced decisions by the PIOs Appellate Authorities and the CIC. It may even lead to unreasonable and absurd orders and bring the institutions created by the RTI Act in disrepute.”
Similarly, the following observation of the Hon’ble Delhi High Court in Bhagat Singh v. CIC & Ors.
WP(C) 3114/2007 are pertinent in this matter:
Page 4 of 5
“17. This Court takes a serious note of the two year delay in releasing information, the lack of adequate reasoning in the orders of the Public Information Officer and the Appellate Authority and the lack of application of mind in relation to the nature of information sought. The materials on record clearly show the lackadaisical approach of the second and third respondent in releasing the information sought. However, the Petitioner has not been able to demonstrate that they malafidely denied the information sought. Therefore, a direction to the Central Information Commission to initiate action under Section 20 of the Act, cannot be issued.”
Furthermore, the High Court of Delhi in the decision of Col. Rajendra Singh v. Central Information
Commission and Anr. WP (C) 5469 of 2008 dated 20.03.2009 had held as under:
“Section 20, no doubt empowers the CIC to take penal action and direct payment of such compensation or penalty as is warranted. Yet the Commission has to be satisfied that the delay occurred was without reasonable cause or the request was denied malafidely.
……The preceding discussion shows that at least in the opinion of this Court, there are no allegations to establish that the information was withheld malafide or unduly delayed so as to lead to an inference that petitioner was responsible for unreasonably withholding it.”
The Appellant could not substantiate his claims regarding malafide denial of information by the
Respondent or for withholding it without any reasonable cause.
DECISION:
Keeping in view the facts of the case and the submissions made by both the parties, it was noted that
no clear and cogent replies had been offered by the Respondent and there was an element of
vagueness in its replies. The Commission therefore instructs the Respondent MoP&NG and GAIL
Gas Ltd. to re-examine the RTI application in depth and provide a clear, cogent and reasoned
response to the Appellant in accordance with the provisions of the RTI Act, 2005 within a period of
15 days from the date of receipt of this order as agreed.
The Commission also instructs the Respondent Public Authority to convene periodic
conferences/seminars to sensitize, familiarize and educate the concerned officials about the relevant
provisions of the RTI Act, 2005 for effective discharge of its duties and responsibilities.
The Appeal stands disposed accordingly. (Bimal Julka) (िबमल जु का) (Information Commissioner) (सूचना आयु )
Authenticated true copy
(अ भ मा णत स या पत त) (K.L. Das) (के .एल.दास)
(Dy. Registrar) (उप-पंजीयक)
011-26182598/ [email protected] दनांक / Date: 19.06.2019 Page 5 of 5